Kazakhstan is gearing up for a significant project aimed at the extraction of iron ore from the Lomonosovskoye deposit, located in the Kostanay region. According to financial reports from the company managing the site, preparations for mining operations are set to commence, with the first extraction planned for 2029 after years of inactivity. The report indicates that the amendment to the mining contract is in its final stages of approval, which includes a working programme extending until December 31, 2046, and plans for the construction of a beneficiation plant.
The timeline for the project outlines that preparatory work will be conducted until the end of 2026, followed by stripping operations from 2026 to 2028, without any concurrent ore extraction. The proposed beneficiation plant is expected to have a capacity of 16 million tonnes of iron ore per year, and the project has already received preliminary approval from the Ministry of Industry.
Originally acquired by the Austrian company Safin Handelsges. GmbH in 2008, the Lomonosovskoye deposit was initially projected to produce 6 million tonnes of iron ore annually starting in 2015. However, plans changed, and the asset was put up for sale in 2010. In 2011, Canadian firm Newbridge Capital Inc. purchased the majority stake for $70.3 million, while retaining a 15% share for Safin Handelsges. As of the end of 2025, Kazco Beteiligungs GmbH, linked to Kazax Minerals Inc., holds a 99.99% stake in the deposit, with the remaining shares held by minority investors.
The mining contract for Lomonosovskoye was originally signed in 2009 for a duration of 21 years, allowing for five years of exploration. The reserves were officially approved at 177 million tonnes of iron ore by the state commission in 2015. Subsequent assessments indicated measured and inferred resources of 507.8 million tonnes as of October 31, 2014. The project has faced delays, including a two-year conservation period initiated in 2016, but has recently made strides towards resuming operations.
Future cash flow projections for the project are based on key assumptions, including an iron ore price of $100 per tonne. The total expected ore production over the life of the deposit is estimated at 275.3 million tonnes, with a projected output of 73.5 million tonnes of iron concentrate containing 67% iron. The project aims to gradually increase production capacity to reach an annual extraction of 22 million tonnes in the later years of operation. Overall, the project’s implementation cost is estimated to be around $1.5 billion, highlighting its significance in Kazakhstan’s mining sector.